DEDICATED PRESSURE SYSTEMS LTD.

Telephone 01372 803 675
Fax 01372 803 678
Email dps@heatweb.com
 
Internet http://www.heatweb.com

The Institute of Plumbing

R/O Shops, 9-19 Manor Green Road, Epsom, Surrey KT19 8RA
  

Installation Instructions
Dual Fuel Heat Bank Thermal Store

3395-1  13/02/01

Heat Bank Thermal Store System  
Xcel unit for connection to remote F+E  
Single Heat Exchanger (30 ltr/min)  
Directly heated from remote source  
40mm Foam Insulation  
GX-Plan primary controls  
Directly Pumped Heating Circuit  
Fitted Primary Pump, 5m head  
All fitted controls are wired  
Thermostatic Blending Valve 22mm  
Backup Immersion Heater  
Cased  


2   Plate Heat Exchanger
3   Heat Exchanger Pump
4   Flow Switch
5   Thermostatic Blending Valve, Mixcall III
6   Manual Air Vent
8   Vent
11  Y-Pattern Strainer (supplied loose)
13  Cold Feed / Expansion
14  Immersion Heater 3kW Incaloy with Stat
16  Cold Mains In, 22mm
17  Hot Mains Out, 22mm
18  Drain Cock
19  Flow From Boiler
20  Return to Boiler
23  Flow to Heating Circuit
24  Return from Heating Circuit
27  Boiler Pump UPS 15/50
28  Heating Circuit Pump UPS 15/60
38  Cylinder Immersion Thermostat
39  White Coated Steel Casing
41  Primary Blending Valve
42  Wiring Centre

 

Unit ID

XC-210-3395-1

Capacity

210

Base Diameter

450

Overall Diameter

530

Height

1550

Contents:
1. Introduction
2. General Requirements
3. Mains Water Supply
4. Connections:
5. Wiring
6. Filling
7. Commissioning
8. Fault Finding
9. Servicing
10. Spares
11. User Instructions